HICONICS New Energy has successfully connected the 4MWp photovoltaic power generation project for Sanyao (Zhongshan) Park to the grid.

Company news Dec. 11, 2025
Return

Recently, the 4MWp distributed photovoltaic power generation project for the No. 3 workshop of Sanyao (Zhongshan) Park, built by HICONICS New Energy, has been successfully connected to the grid. Sanyao New Energy Vehicle Components Co., Ltd. is a subsidiary of Sanyao Holding Group, serving as the group's Southern headquarters base and the second largest production base for automotive components. It is also a significant manufacturing and logistics center for global new energy vehicle thermal management. The successful grid connection of this project not only delivers clean electricity to the base but also marks the achievement of the dual goals of 'practicality + green' in the cooperation on commercial and industrial clean energy applications between both parties.

1a276040-c127-415e-a91a-006b53f84d80.jpg 

The project utilizes the roof space of 16,960 square meters on the 3rd workshop of Sanyao (Zhongshan) Park, with a total installed capacity of 4MWp, adopting the 'self-generation and self-use, surplus power to grid' mode, and is independently invested and constructed by the owner. To ensure efficient power conversion and stable transmission, the project is equipped with 5,471 pieces of 720Wp high-efficiency monocrystalline photovoltaic modules, paired with 11 units of 320kW string inverters, connected to the grid at a 10kV voltage level, focusing throughout the process on the reliability and energy efficiency of the power station.

 

 

Notably, the project marks the first application of the cement roof slope arrangement method in HICONICS New Energy construction. This technology breaks the traditional rooftop PV layout limitations, through scientifically designed dual-slope angles and slope surface design, accurately adapting to cement roof structures, reducing redundant space occupation, and achieving efficient utilization of roof area; At the same time, it reasonably distributes the load, increasing the roof load-bearing capacity, and increasing the unit area equipment deployment, achieving maximum capacity; Its smooth drainage and stable structure also reduce long-term maintenance costs and extend the service life, achieving full-chain value-added from short-term investment to long-term operation.

 

 

The project construction progressed efficiently, starting on August 15, 2025, and completing grid connection on November 12, a construction period of less than 3 months, which not only demonstrates HICONICS New Energy's mature capabilities in project planning and construction management but also allows the enterprise to enjoy the benefits of clean energy in advance.

7787de8d-8d96-49d2-a7cc-a08c452410ed.jpg

In terms of environmental benefits, the project is expected to generate a cumulative 107,846,400 kWh of electricity over its 25-year lifecycle, reduce CO₂ emissions by 61,504.80 tons, and save 32,429.41 tons of standard coal. This not only reduces Sanyao Park's electricity costs and ensures a stable energy supply, but also marks a crucial step towards its goal of 'low-carbon production.'

As a practical example in the commercial and industrial photovoltaic sector, the project fully demonstrates HICONICS New Energy's technical and service capabilities, providing a feasible 'green transformation' path for manufacturing enterprises. In the future, HICONICS New Energy will continue to focus on the clean energy sector, offering customized solutions to help more companies transition through an 'energy revolution,' and jointly promote the development of green manufacturing.